G98 vs G99: Which Application Do You Need?

The key difference is capacity. G98 is for systems up to 3.68kW (single-phase). G99 is for anything larger. Here's how to determine which you need.

Check Grid Capacity

G98 vs G99 at a Glance

FeatureG98G99
Capacity Limit≤16A per phase
(3.68kW single / 11.04kW three-phase)
>16A per phase
(No upper limit)
Process TypeConnect & NotifyApply & Connect
DNO Approval Needed?No - install firstYes - before install
Application Fee£0£220 - £8,000+
(varies by DNO & size)
TimelineImmediate install
Notify within 28 days
45-65 working days
(Fast Track: 10-20 days)
Equipment RequiredType Tested inverterType Tested (recommended)
Typical UseResidential solar
Small battery systems
Commercial solar, solar farms
Large battery, V2G

Understanding the 16 Amp Threshold

The dividing line between G98 and G99 is 16 Amps per phase. This translates to:

Single-Phase Supply

3.68 kW

230V × 16A = 3,680W

Most UK homes have single-phase. A typical 3.6kW solar inverter just fits under G98.

Three-Phase Supply

11.04 kW

230V × 16A × 3 = 11,040W

Some larger homes and commercial properties have three-phase, allowing bigger G98 systems.

Important: Aggregate Capacity

The 16A limit applies to total generation capacity at your property, not individual devices. If you have a 3kW solar inverter and add a 2kW battery inverter, your aggregate is 5kW - which exceeds G98 and requires G99.

Common Scenarios: G98 or G99?

G98 (Connect & Notify)

Standard home solar (≤3.6kW inverter)

12 panels with a 3.6kW inverter = G98

Solar + DC-coupled battery

Hybrid inverter outputting max 3.6kW to grid = G98

Three-phase home (≤11kW)

10kW system on 3-phase supply = G98

G99 (Apply First)

Solar + AC-coupled battery

3.6kW solar + 5kW Powerwall = 8.6kW total = G99

Commercial rooftop solar

Any system over 3.68kW (single-phase) = G99

Solar farms & large BESS

Always G99 - typically megawatt scale

V2G (Vehicle-to-Grid) chargers

Bi-directional 7kW charger that exports = G99

G99 Fast Track: The Middle Ground

If your system exceeds G98 limits but is under 32A (7.36kW), you may qualify for G99 Fast Track. This uses export limitation (G100) to cap your grid export at 16A while allowing higher total capacity.

Fast Track TypeTotal CapacityExport LimitExample
SGI-1≤16A (3.68kW)No limit needed1.5kW solar + 2kW battery
SGI-2≤32A (7.36kW)≤16A (3.68kW)3.68kW solar + 3.68kW battery with G100 limiter
SGI-3≤60A (13.8kW)≤32A (7.36kW)Large residential with impedance testing

Fast Track typically takes 10-20 working days for approval, compared to 45-65 days for full G99.

G98 vs G99 Costs (2025/2026)

G98 Costs

£0

No DNO application fee. Your installer may charge £50-150 for completing the notification paperwork.

G99 Costs

Fast Track / Small (<50kW)£0 - £500
Commercial LV£220 - £3,000
HV/EHV Projects£1,300 - £8,000+

Fees vary by DNO. Additional costs may apply if grid reinforcement is required.

Planning a Solar or Battery Installation?

Check your local grid capacity before committing. Our free tool shows available capacity at your nearest substation.

Check Grid Capacity

Frequently Asked Questions

G98 is limited to 16 Amps per phase, which equals 3.68kW for single-phase supplies or 11.04kW for three-phase supplies. This is the maximum inverter AC output capacity, not the DC panel capacity.
It depends on the total inverter capacity. If your solar inverter (e.g., 3.6kW) plus battery inverter (e.g., 3kW) exceeds 3.68kW combined, you need G99. However, a hybrid inverter with DC-coupled battery that outputs max 3.68kW to the grid qualifies for G98.
Standard G99 applications take 45-65 working days (approximately 3 months) for the DNO to issue a Connection Offer. Fast Track G99 (for systems under 32A with export limiting) can be approved in 10-20 working days.
G99 Fast Track (also called SGI - Small Generation Installation) allows systems up to 32A (7.36kW) with export limited to 16A (3.68kW) using G100 export limitation. This avoids the lengthy full G99 study while allowing larger system capacity.
Standard EV chargers are loads, not generators, so they do not require G98/G99. However, Vehicle-to-Grid (V2G) chargers that can export power back to the grid do require G99 if they exceed 3.68kW export capacity.
Non-compliance can result in DNO disconnection, inability to receive Smart Export Guarantee payments, voided insurance, and delays when selling your property. The DNO acknowledgement letter is required for SEG tariff registration.

Need Help with Your Grid Connection?

Whether you need G98 or G99, understanding your local grid capacity is the first step. Our free tool helps you assess viability before you invest.

Check Grid Capacity