How Big Is the UK Grid Connection Queue?

743 GW of power projects are contracted to connect to the GB grid, but only 81 GW is actually built and 74.2% has not even reached a planning application. Here is what the queue looks like, and why a real grid connection is the scarcest thing a solar or battery developer needs from your land.

Source: NESO TEC register · 2,217 projects · Updated 5 June 2026

How big is the UK grid connection queue?

As of 5 June 2026, 743 GW of generation and storage is contracted to connect to the GB transmission grid across 2,217 projects. Only 81 GW is built and connected; the other 661 GW is still in the queue. Crucially, 74.2% of all contracted capacity (551 GW) is at the earliest "Scoping" stage, meaning NESO is not aware of a planning application for it. Solar accounts for 237 GW, of which 94.7% is co-located with battery storage.

The takeaway for landowners: capacity on paper is abundant, but a deliverable grid connection is scarce, and that is what a developer is really paying for. Land that already sits near available grid capacity is worth far more than a speculative queue position. Check where your land stands.

The queue at a glance

742.6 GW
Total contracted capacity
2,217
Projects in the register
81.4 GW
Actually built & connected
74.2%
Still speculative (Scoping)
236.9 GW
Solar PV in the queue
94.7%
Of queued solar paired with batteries

Where the queue actually stands

Most of the headline capacity is nowhere near being built. Projects move through five stages, from speculative "Scoping" to "Built". Only 81.4 GW of the 742.6 GW total is energised today.

Project statusCapacity (GW)ProjectsShare of GW
Scoping551.21,51774%
Awaiting Consents58.61528%
Consents Approved48.11686%
Under Construction/Commissioning3.4200%
Built81.436011%

What is in the queue, by technology

Battery storage dominates the pipeline, and the great majority of new solar is now paired with it. Because co-located sites carry more than one technology, a solar-plus-battery project is counted under both, so these figures overlap and do not sum to the total.

TechnologyCapacity (GW)Projects
Battery / energy storage479.91,516
Solar PV236.9618
Offshore wind134.2152
Onshore wind84.4520
Gas (CCGT / OCGT)81.3100
Nuclear33.129
Interconnectors5.43

When projects are contracted to connect

Connection dates for unbuilt projects stretch well into the 2030s. This is the queue "stretching out": far more capacity is contracted than the grid can absorb in any one year, so dates slip years into the future.

2024
1.5 GW
2025
8.9 GW
2026
18.1 GW
2027
23.5 GW
2028
39.7 GW
2029
47.7 GW
2030
41.7 GW
2031
56.3 GW
2032
36.2 GW
2033
89 GW
2034
79.4 GW
2035
66.4 GW
2036
34.2 GW
2037
94.3 GW
2038
18 GW
2039
5.3 GW

Where the queue clusters

The connection points (grid supply points and transmission substations) with the most contracted capacity. These are the parts of the network developers are competing hardest to connect to.

#Connection siteContracted (GW)Projects
1Alverdiscott 400kV Substation1819
2Creyke Beck 400kV Substation9.17
3Norwich Main 400kV Substation8.47
4Drax 400kV Substation8.23
5Grimsby West 400kV Substation6.67
6Longside 400kV Substation6.56
7Trent Valley South Connection Node D 400kV Substation6.44
8East Claydon 400kV Substation6.27
9Branxton 400kV Substation5.85
10Navenby 400kV Substation5.710
11Trent Valley South Connection Node B 400kV Substation.5.410
12Birkhill Wood 400kV Substation5.25
13Eggborough 400kV Substation5.24
14Cheshire Connection Node A 400kV Substation5.14
15Greens 400kV Substation5.14

What this means if you own land

  • A grid connection is the real prize. With 551 GW of speculative capacity chasing limited network headroom, developers value land that can actually connect, not another paper queue position.
  • Expect solar-plus-battery. 94.7% of queued solar is co-located with storage, so an approach for your land will often be for a combined scheme.
  • Proximity to capacity beats acreage alone. A smaller site near available grid capacity can be more attractive than a large site far from it.
  • Timelines are long. Connection dates run into the 2030s, so option agreements and exclusivity periods are written around multi-year horizons.

Methodology & caveats

  • Source: the National Energy System Operator (NESO) Transmission Entry Capacity (TEC) register, pulled live from the NESO data portal API and last updated by NESO on 5 June 2026.
  • Scope: the TEC register covers projects connecting to (or affecting) the high-voltage transmission network. It captures large generation and storage projects but not smaller, distribution-connected sites, which sit on each network operator's Embedded Capacity Register. Figures here therefore describe the national, large-scale queue.
  • Capacity: based on each project's "Cumulative Total Capacity (MW)". Staged projects (which appear as several rows) are de-duplicated to one record each, so capacity is not double-counted. 2,218 register rows resolve to 2,217 distinct projects.
  • Technology buckets overlap. "Plant Type" can list several technologies for a co-located site. A solar-plus-battery project is counted under both solar and storage, so the technology rows do not sum to the total. The non-overlapping totals are the headline figures.
  • Status: as classified by NESO. "Scoping" means NESO is not aware of a planning application; "Awaiting Consents" means one has been made; "Consents Approved" means it has been granted. These are recorded on an "as far as we are aware" basis.
  • No site geography. The TEC register locates projects only by their connection point (a grid supply point or substation name), not by postcode or coordinates, so this page does not map projects to your specific area. For a location-based view, use the grid capacity check.

How to cite this data

This dataset is free to quote with a link. Suggested citation:

SolarGridCheck (2026). The UK Grid Connection Queue. Derived from the NESO Transmission Entry Capacity (TEC) register (5 June 2026). https://solargridcheck.co.uk/uk-grid-connection-queue

Frequently asked questions

How big is the UK grid connection queue?

About 743 GW of generation and storage is contracted to connect to the GB transmission grid across 2,217 projects, but only 81 GW is built and connected today. The rest, roughly 661 GW, is still working through the queue.

Why is the grid queue so much bigger than what is needed?

Much of it is speculative. 74.2% of all contracted capacity (551 GW) is at the "Scoping" stage, where NESO is not aware of any planning application. Historically it cost little to hold a queue position, so far more capacity was contracted than the network can absorb, which is what connections reform is now trying to fix.

How much solar is in the grid connection queue?

Solar PV accounts for about 237 GW across 618 projects. Of that, 94.7% is co-located with battery storage, so most new solar in the queue is part of a combined solar-and-battery scheme.

What does the grid queue mean for landowners?

It means a deliverable grid connection, not land area on its own, is the scarce resource developers pay for. Land near available grid capacity is far more attractive than a speculative queue position. The free grid capacity check shows where your land sits relative to nearby substations.

What is the TEC register?

The Transmission Entry Capacity (TEC) register is published by the National Energy System Operator (NESO). It lists projects that hold, or are contracted to hold, capacity rights on the GB transmission network, with each project's capacity, connection point and build status. This page aggregates the register into a national picture of the connection queue.