news

UK Grid Connection Queue 2026: 500GW Backlog, Reform Impact & What It Means For Your Project

The UK grid connection queue has 500GW+ of projects waiting, with connection dates of 2030-2036 in congested areas. The 'First Ready, First Connected' reform is clearing zombie projects. Here's what changed, who benefits, and how to improve your queue position.

The SolarGridCheck Team
12 min read

Grid Connection Queue 2026: Key Facts

The UK grid connection queue has a 500GW+ backlog of projects, with connection dates of 2030-2036 in many areas. The "First Ready, First Connected" reform is replacing the old first-come-first-served system, terminating zombie projects that hold capacity without building. To maintain your position, you must pass Gate 2 assessment with evidence of land rights and planning progress. Projects with planning permission are now prioritised. Connection costs range from £50,000 to £2,000,000+ depending on voltage level and reinforcement needs.

The UK grid connection queue is the single biggest bottleneck for solar farm and battery storage development. Over 500GW of projects are waiting — more capacity than the entire UK electricity system needs. Here's what's changing in 2026, who benefits from the reforms, and how to position your project for the fastest possible connection.

Check your land's solar potential

Our free grid capacity checker shows estimated income based on your location and land size.

Calculate Now

What Went Wrong With the Grid Connection Queue?

The UK grid connection queue was designed for a world of large, centralised power stations. The explosion of solar, wind, and battery storage projects overwhelmed a system never built to handle thousands of simultaneous applications.

The result:

  • 500GW+ in the queue — the UK's peak demand is approximately 60GW, meaning there is over 8x more capacity in the queue than the country actually needs
  • Connection dates of 2030-2036 in the most congested areas (South East, East Anglia, South West)
  • Zombie projects — speculative applications from developers who applied for grid capacity with no intention or ability to build, blocking viable projects behind them
  • Rising costs — reinforcement costs passed to developers (and ultimately landowners via lower lease terms) as DNOs struggle to upgrade infrastructure fast enough

What Is "First Ready, First Connected" and How Does It Work?

The "First Ready, First Connected" reform replaces the old first-come-first-served queue with a system that prioritises projects most likely to actually build. Under the old system, you could hold a queue position indefinitely by simply paying the initial assessment fee. Under the new system, you must demonstrate genuine progress or lose your place.

Gate 2: The Readiness Test

Gate 2 is the critical checkpoint. To pass Gate 2 and secure a firm connection date, a project must demonstrate:

  • Land rights: A signed option agreement or lease with the landowner, verified by a Letter of Authority submitted to the DNO
  • Planning progress: Evidence that planning permission has been applied for, is in pre-application consultation, or has been granted. Projects with granted planning permission receive priority.

Projects that cannot demonstrate both land rights and planning progress at their Gate 2 assessment are terminated. Their grid capacity is immediately freed and reallocated to the next ready project in the queue.

User Progression Milestones

Even after passing Gate 2, projects must meet strict deadlines called User Progression Milestones. These include:

  • Accepting the connection offer within the specified deadline (typically 30-90 days)
  • Paying the required deposit on time
  • Achieving planning permission by the milestone date
  • Commencing construction by the specified date

Missing any milestone results in automatic termination — no appeals, no extensions. This prevents projects from passing Gate 2 and then stalling.

Who Benefits From the Queue Reforms?

Good news for serious developers and landowners:

If you have planning permission and a signed land agreement, your connection date may improve significantly as zombie projects are terminated and capacity is freed up. Projects that were facing 2034-2036 connection dates may see these pull forward by several years.

Winners under the new system:

  • Projects with planning permission: Prioritised at Gate 2. If you've already secured planning, you jump ahead of speculative applications.
  • Landowners with signed agreements: Developers need your signed Letter of Authority to pass Gate 2. This strengthens your negotiating position.
  • BESS projects: Battery storage can sometimes access capacity faster because they can both import and export, making them useful to grid operators managing congestion.
  • Projects near substations: Shorter connection distances mean lower reinforcement costs and faster physical connection once the grid offer is secured.

Losers under the new system:

  • Speculative developers: Those who applied for grid capacity without land or planning. Their positions are being terminated.
  • Stalled projects: Developers who secured a connection offer years ago but never progressed to construction. Milestone requirements will force them to build or lose position.

Grid Connection Queue by DNO Area: Where Are the Biggest Backlogs?

The queue backlog varies dramatically by Distribution Network Operator (DNO) area. Understanding your local DNO's position is critical for realistic project planning:

DNOCoverageQueue StatusEarliest New Connection
UK Power Networks (UKPN)South East, East, LondonSeverely constrained2032-2036
Western Power Distribution (NGED)Midlands, South West, WalesHeavily constrained2030-2034
Northern PowergridNorth East, YorkshireModerately constrained2029-2032
Electricity North WestNorth West EnglandModerately constrained2029-2032
Scottish Power Energy NetworksCentral & Southern ScotlandModerately constrained2028-2031
SSE NetworksNorth Scotland, Southern EnglandLess constrained (parts)2028-2031

Critical insight: These are averages across each DNO area. Within a single DNO region, one substation may have capacity available by 2028 while another 10 miles away may be full until 2035. This is why site-specific grid checking — not regional assumptions — is essential. Use our grid capacity checker to see what's available near your specific location.

Case Study: How Queue Reform Accelerated a 30MW Solar Farm in Wiltshire

A 30MW solar project near Salisbury initially received a 2034 connection date. The developer had already secured planning permission (granted 2024) and a signed land option. When Gate 2 assessments commenced, three speculative projects ahead in the queue — totalling 85MW of capacity held without land agreements — were terminated. The project's connection date was revised forward to 2029, saving 5 years. The earlier connection date increased the project's NPV by approximately £4.2 million due to earlier revenue generation and reduced financing costs.

How Does the Queue Affect Grid Connection Costs?

Grid connection costs are driven by two factors: the physical infrastructure needed (cables, switchgear, transformers) and the reinforcement required to the existing network. Both are affected by the queue:

Connection TypeCost RangeScenario
11kV (near substation)£50,000 - £150,000Best case — available capacity, short cable run
11kV (reinforcement needed)£150,000 - £500,000Common — local network at capacity
33kV connection£300,000 - £1,000,000Larger solar farms 10MW+
Major reinforcement£1,000,000 - £2,000,000+New substation or major upgrade required

As zombie projects are cleared from the queue, some reinforcement costs may decrease because the network was being sized for capacity that will never be built. However, this effect will take time to materialise and varies significantly by DNO area.

Ready to see what your land could earn?

Get an instant estimate of your potential solar farm income based on grid capacity in your area.

Calculate Now

What Should Landowners and Developers Do Now?

  1. Check your grid capacity first. Use a grid capacity checker to understand what grid infrastructure is near your land. Proximity to a substation with available capacity is the single biggest factor in connection cost and timeline.
  2. Progress planning early. Under the new rules, planning permission is the key differentiator. Projects with planning are prioritised at Gate 2. Apply for planning as early as possible — it can take 12-18 months. See our planning permission guide.
  3. Secure land agreements. Developers need a signed Letter of Authority to pass Gate 2. If you're a landowner, ensure your option agreement or lease is properly documented. This is now a Gate 2 requirement, not just a formality.
  4. Consider flexible connections. Active Network Management (ANM) allows you to connect sooner by agreeing to occasional curtailment during network congestion. The lost generation during curtailment (typically 2-5% of annual output) is often worth it for a connection date years earlier.

    ANM Curtailment: The Financial Trade-Off

    A 10MW solar farm generating 9,500 MWh/year at £60/MWh earns £570,000/year. With ANM curtailment of 3%, annual generation drops to 9,215 MWh — a revenue reduction of £17,100/year. However, if ANM brings your connection date forward by 4 years, you earn £2,280,000 in revenue (4 years × £570,000) that would otherwise be lost to waiting. The cost of curtailment over a 25-year operating period is approximately £427,500 — meaning ANM delivers a net benefit of £1.85 million versus waiting for a firm connection.

  5. Consider battery storage. BESS projects often face shorter grid queues because they provide grid-balancing services. If your land has 33kV+ proximity, battery storage may offer both faster connection and higher per-acre income.
  6. Get a budget estimate before committing. A feasibility study from the DNO (usually free or minimal cost, 10-20 working days) tells you whether there is available grid capacity before you invest in detailed designs. See our G99 application guide for the full process.

Check Your Land's Solar Potential

Our free grid capacity checker analyzes your location and shows you exactly what your land could earn from solar development.

Calculate Now

Grid Connection Queue FAQs

Frequently Asked Questions

The UK grid connection queue currently has over 500GW of projects waiting to connect. Many areas have connection dates of 2030-2036. The backlog is largely caused by speculative applications from projects that never intended to build — so-called 'zombie projects' that hold queue positions without progressing.
The old 'first-come, first-served' queue is being replaced by a 'First Ready, First Connected' system. Projects must now demonstrate genuine progress — specifically land rights and planning permission — to maintain their queue position. Projects that cannot show progress at Gate 2 assessments are being terminated and their grid capacity freed for viable projects.
Gate 2 is a checkpoint where projects must demonstrate they meet readiness criteria to secure a firm connection date. Requirements include evidence of land rights (signed option or lease agreement) and planning progress (pre-application, submitted, or granted). Projects that fail Gate 2 lose their queue position and the capacity is reallocated.
Yes, but connection dates for new applications are typically 2030-2036 in congested areas. The reforms may improve this as stalled projects are cleared. Having planning permission significantly helps your position under the new 'First Ready, First Connected' system. Consider flexible connections with Active Network Management (ANM) for potentially faster access.
Grid connection costs range from £50,000 for an 11kV connection near a substation to over £2,000,000 for projects requiring major substation reinforcement. Assessment fees are £500-£2,500 (HV) or £3,000-£8,000+ (EHV/33kV+). These fees are non-refundable even if you decide the cost is too high.
New connection offers include 'User Progression Milestones' with strict deadlines. Missing a milestone results in automatic termination of your grid connection offer. You cannot appeal — the capacity is immediately reallocated. This is intentionally strict to prevent projects from holding positions indefinitely without building.

Ready to Check Your Land's Solar Potential?

Our free grid capacity checker shows you exactly what your land could earn from solar.

Calculate Now