guides

G99 Application UK: Avoid Rejection — Costs by DNO & 2026 Reforms

G99 fees vary by DNO (£500–£8k+). 61% of queue projects just got cut. Practical guide: DNO-by-DNO comparison, 5 rejection causes, 4 options after rejection, and the Gate 2 timeline that matters for 2026.

The SolarGridCheck Team
18 min read

G99 Application: Quick Answer

A G99 application is required for any UK power generation installation over 3.68kW per phase, including all solar farms, commercial solar, and battery storage systems. Assessment fees range from £500–£8,000+ (non-refundable, varies by DNO), with connection costs from £50,000 to over £2,000,000. The UK grid queue has been slashed from 722GW to 283GW under 2026 reforms — good news if your project is viable, but you must now pass Gate 2 criteria to secure a connection date.

  • Who needs G99: Any installation over 3.68kW per phase (all solar farms, commercial solar, BESS)
  • Assessment fees: £500–£2,500 (HV) or £3,000–£8,000+ (EHV/33kV+) — non-refundable
  • Connection costs: £50,000–£2,000,000+ depending on distance and reinforcement
  • DNO timeline: 10 days (fast track) to 45–65 working days (full G99) — but real-world reports range from 1 day to 6 months
  • Queue reform: 61% of projects cut. "First Ready, First Connected" replaces first-come-first-served
  • Gate 2 offers: Transmission offers May–Sep 2026, distribution offers Jul–Nov 2026
  • If rejected: 4 options — G100 export limitation, fund reinforcement, flexible/ANM connection, or reapply later

If you're developing a solar farm or large-scale renewable energy project in the UK, you'll need to navigate the G99 grid connection process. This guide explains everything you need to know about G99 applications, from initial feasibility to final energisation - including the queue management reforms that are reshaping how projects get connected.

Check your land's solar potential

Our free grid capacity checker shows estimated income based on your location and land size.

Calculate Now

What Is a G99 Application?

A G99 application is the formal process for connecting power-generating equipment over 3.68kW per phase to the UK electricity distribution network. G99 (Engineering Recommendation EREC G99) replaced the older G59 standard in April 2019 and applies to all large-scale generation including solar farms, wind turbines, and battery storage systems. Every solar farm in the UK requires G99 approval from the local Distribution Network Operator (DNO) before installation can begin.

You must submit a G99 application if your project meets any of the following criteria:

  • Capacity over 3.68kW per phase (single-phase) or over 11.04kW (three-phase)
  • Any commercial solar installation - even with zero export, the installed capacity dictates the application type
  • Non-type tested equipment - common for large-scale solar inverters

The key difference from smaller installations is that G99 requires formal DNO (Distribution Network Operator) approval before you can install. You cannot simply install and notify as you would with a residential system.

G99 vs G98: Which Do You Need?

The choice between G99 and G98 depends primarily on your system size:

FeatureG98 (Micro-generation)G99 (Large Scale)
System Size<3.68kW per phase>3.68kW per phase
Process"Install and Notify" (within 28 days)"Apply and Wait" (approval before install)
Typical UserResidential rooftopSolar farms, commercial, batteries
CostFreeApplication fees + connection charges
TimelineImmediate installation3+ months for offer, years for connection

For solar farms, there's no question - you'll need G99. Even a modest 50kW commercial rooftop system requires G99 approval.

For a more detailed breakdown of the differences, including Fast Track options and common scenarios, see our dedicated G98 vs G99 comparison guide.

What Is the G99 Application Process?

The G99 application process has five phases: feasibility study (10-20 working days), formal application via Standard Application Form (45-65 working days for DNO response), connection offer acceptance (30-90 days to decide), construction and commissioning (6-24 months), and operational notification. The total process from initial enquiry to energisation typically takes 2-5 years for solar farm projects.

Phase 1: Feasibility & Budget Estimate (Optional but Recommended)

  • Action: Apply for a "Budget Estimate" or "Feasibility Study" from your local DNO
  • Outcome: A rough cost estimate (±50%) and indication of available grid capacity
  • Timeline: 10-20 working days
  • Cost: Usually free or minimal fee

This step is crucial for solar farms. It tells you whether there's grid capacity in your area before you invest in detailed technical designs. Many projects discover at this stage that local infrastructure is constrained.

Phase 2: Formal Application

  • Action: Submit the Standard Application Form (SAF) to the local DNO
  • Requirement: You must demonstrate "Land Rights" with a Letter of Authority from the landowner
  • Timeline: DNO has 45-65 working days (approximately 3 months) to issue a Connection Offer

Phase 3: Connection Offer & Acceptance

  • Action: DNO issues a formal "Connection Offer" detailing costs, connection date, and required works
  • Decision: You typically have 30-90 days to accept and pay the deposit
  • Important: New offers include "Queue Management Milestones" - miss these and you lose your place

Phase 4: Construction & Commissioning

  • Action: Build the solar farm (DNO may need to complete reinforcement works first)
  • Timeline: 6-24 months depending on project size
  • Milestone: G99 Witness Testing - DNO engineers visit site to witness protection tests

Phase 5: Operational Notification

  • Action: Submit Form B3 (final commissioning forms)
  • Outcome: DNO issues "Final Operational Notification" (FON) - you are now live

Ready to see what your land could earn?

Get an instant estimate of your potential solar farm income based on grid capacity in your area.

Calculate Now

What Documents Do You Need for a G99 Application?

A G99 application requires three essential documents: a Single Line Diagram (SLD) showing the electrical schematic, a Letter of Authority signed by the landowner, and evidence of planning status. Additional technical data includes inverter datasheets, fault level analysis, protection settings, and proposed cable routes. For solar farm projects, prepare the following:

Essential Documents

  • Single Line Diagram (SLD): Professional electrical schematic showing point of connection, protection relays, and isolation points
  • Letter of Authority: Signed by landowner granting developer permission to apply
  • Planning Status: Evidence of planning application or pre-application advice (now critical for queue position)

Technical Data Required

  • Inverter datasheets with PQ diagrams and fault ride-through capabilities
  • Maximum Export Capacity (MEC) required
  • Earthing arrangements
  • Protection settings and relay specifications
  • Proposed cable routes and lengths

Pro Tip:

For projects over 50kW, hire a specialist electrical consultant. Errors in technical documentation are a leading cause of delays and rejections.

How Much Does a G99 Application Cost? (2026 Rates)

G99 application costs have two components: assessment fees (£500-£8,000+, non-refundable) and connection charges (£50,000-£2,000,000+). Assessment fees cover the DNO's design work to produce a Connection Offer. Connection charges cover the physical infrastructure — cables, switchgear, and any substation reinforcement required.

A. Assessment & Design Fees

Most DNOs charge upfront just to process the application:

  • HV (High Voltage) Connection: £500 - £2,500
  • EHV (Extra High Voltage) / 33kV+: £3,000 - £8,000+

Note: These fees are non-refundable even if the connection cost is too high to proceed.

B. Witness Testing Fees

  • Standard Rate: Approximately £957 + VAT per visit
  • Rates vary slightly by DNO (UK Power Networks, SSEN, National Grid, etc.)

C. Connection Charges (The Major Cost)

  • Reinforcement: If the local substation needs upgrading, you may pay a share
  • Sole Use Assets: You pay 100% for assets installed just for your site
  • Typical Solar Farm Cost: £50,000 to £2,000,000+ depending on distance to substation and voltage level
Connection TypeTypical Cost RangeNotes
11kV (near substation)£50,000 - £150,000Best case scenario
11kV (reinforcement needed)£150,000 - £500,000Common scenario
33kV connection£300,000 - £1,000,000For larger solar farms
Major reinforcement£1,000,000 - £2,000,000+New substation required

G99 by DNO: Fees, Timelines & Quirks

Each DNO handles G99 applications differently. Official guides won't tell you this, but turnaround times, admin fees, and capacity vary significantly. Here's what we've found from real-world data and published DNO documents:

DNORegionFast Track TargetGate 2 Ph1 CapacityNotes
NGEDMidlands, SW England, WalesNot published6,546 MWLargest DNO allocation. Published Network Opportunity Map and EHV constraint maps. Witness testing ~£957+VAT/visit.
UKPNLondon, SE & E EnglandNot published3,085 MWHighest Ofgem incentive payment (£12.6M). Rolling out centralised ANM for flexible connections.
Northern PowergridNE England, Yorkshire10 days (fast track)2,130 MWQuickest real-world turnarounds — some fast-track approvals in 1 day. 45 days for full G99.
SSENScotland, S England10 daysN/A (distribution)Separate regional contacts for Scotland vs England. Requires FO-NET-CAB-008 form for SGI-3 applications.
SP Energy NetworksCentral/S Scotland, NW EnglandNot publishedN/AHighest reported installer admin fees (£250–£750). Only charges DG applicants for assessment.
ENWLNW EnglandNot publishedN/APublished detailed witness testing guide. Modest LV works charges.

Real-World vs Official Timelines

DNOs publish 45–65 working day targets for full G99 offers. In practice, we've seen Northern Powergrid issue fast-track approvals in 1 day, while standard G99 applications with other DNOs can take 4–6 months. Always budget for the longer estimate.

Check your land's solar potential

Our free grid capacity checker shows estimated income based on your location and land size.

Calculate Now

The 2026 Grid Queue Crisis (& Reform)

The UK grid queue has undergone the biggest reform in its history. The pre-reform queue held 722GW of projects — four times what the UK needs to hit its 2030 clean energy targets. Under the new "First Ready, First Connected" system, that's been slashed to 283GW — a 61% reduction. If your project is viable, this is the best news in years.

The Numbers Behind the Reform

Pre-reform queue722 GW (mostly speculative "zombie projects")
Post-reform allocation283 GW (132 GW by 2030, 151 GW by 2035)
Gate 1 waiting list216 GW still queuing for Gate 2 assessment
Battery storage cut153 GW of BESS projects deprioritised or removed
Solar not prioritised35.9 GW of solar projects did not make the cut

Gate 2 Timeline: When Offers Are Being Issued

Gate 2 is the mechanism that replaced first-come-first-served. To secure a firm connection date, your project must pass Gate 2 criteria — land rights + planning permission (or advanced progress). Offers are being issued now:

  • Transmission offers (Phase 1): Mid-May to mid-September 2026
  • Distribution offers (Phase 1): Early July to mid-November 2026
  • Transmission offers (Phase 2): Early September 2026 to mid-January 2027
  • Distribution offers (Phase 2): Mid-October 2026 to mid-March 2027
  • Next application window: Q2 2026 at earliest (delayed from original timeline)

The Data Centre Problem

A new threat to the queue: data centre demand surged from 41GW (November 2024) to 125GW (June 2025). Around 50GW of data centres now sit in the connection queue — exceeding the UK's entire peak electricity demand of 45GW. The government has designated "AI Growth Zones" as strategically important, giving them queue priority. This directly competes with renewable energy projects for connection dates.

What This Means for Your Project

  • 8 milestones now track progress from planning consent through construction — miss one and you lose your place
  • 90 days to respond to transmission connection offers (non-negotiable)
  • Projects with planning permission + secured land are being fast-tracked through Gate 2
  • Projects without both are being held in the Gate 1 waiting list or terminated

Good News for Serious Developers

The 61% queue reduction means viable projects are getting connection dates years earlier than expected. If you have planning permission and land secured, apply now — the window is the best it's been since the queue backlog began.

Ofgem Consultation (Live)

Ofgem's February 2026 consultation on demand connection reform closed 13 March 2026. A government consultation closes 15 April 2026. Expected changes: tougher financial requirements including refundable deposits, progressive commitment fees, and upfront non-refundable deposits to deter speculative applications. Decision expected spring 2026.

Why Do G99 Applications Get Rejected?

G99 applications are rejected for five main reasons. The first two are technical constraints you can check before applying. The last three are preventable errors that waste months:

1

"Thermal Constraints" — local network at capacity

The cables and transformers can't handle more export. Requires millions in reinforcement. Prevention: Check DNO heat maps before applying — NGED's Network Opportunity Map, UKPN's Open Data Portal, and GB Grid Data all show capacity by area.

2

"Reverse Power Flow" — blocked at Grid Supply Point

Too much generation trying to export upstream. Prevention: Request a Budget Estimate (Phase 1) before committing to a full application. This is free or low-cost and reveals the constraint early.

3

Incomplete or incorrect documentation

Missing single line diagrams, wrong MPAN numbers, outdated inverter type test certificates. A single MPAN typo can derail an entire application. Prevention: Hire a specialist for anything over 50kW. Double-check inverter certificates are current (they expire).

4

Speculative application without genuine land rights

DNOs now rigorously verify Letters of Authority. The queue reform was specifically designed to eliminate "zombie projects" holding capacity without intent to build. Prevention: Secure a signed LoA before applying — and ensure your planning application is progressing.

5

Non-compliant inverter equipment

Inverters missing fault ride-through capability or G99-compliant protection settings. "Off-grid" inverters generally cannot get G99 certification at all. Prevention: Only specify type-tested, G99-compliant inverters with current certificates.

4 Options After G99 Rejection (Ranked by Speed & Cost)

A G99 rejection isn't the end. Most guides bury this information, but you have four clear paths forward — and one of them is often the smartest option even before you get rejected:

Option 1: Accept G100 Export Limitation (Fastest, Cheapest)

Install a larger system but cap grid export at a lower threshold (e.g., install 7.36kW but limit export to 3.68kW). You benefit from higher self-consumption while staying within grid limits. Cost: £300–£700 for the G100 application.

Best for: Commercial rooftop systems with high self-consumption (warehouses, factories, offices). Around 10% of G99 applications end up with export limitation — but it's increasingly a strategic choice, not just a fallback.

Option 2: Request a Flexible/ANM Connection (Moderate Cost, Faster Connection)

Agree to Active Network Management (ANM) where the DNO can remotely curtail your output during rare peak congestion periods. Typically curtailment is under 5% of annual generation. UKPN is rolling out centralised ANM across its network.

Best for: Solar farms in constrained areas. You get connected years sooner, lose minimal generation, and avoid paying for grid reinforcement.

Option 3: Fund Grid Reinforcement (Expensive, Full Capacity)

Pay for the infrastructure upgrades needed to accommodate your full export capacity. This can mean new cables, switchgear, or even substation upgrades. Cost: £150,000–£2,000,000+.

Best for: Large utility-scale projects where the business case supports the capital expenditure and full export is commercially critical.

Option 4: Reapply Later (Free, Uncertain)

Grid conditions change as other projects drop out or reinforcement works complete. The 2026 queue reforms are actively terminating stalled projects, freeing capacity. Check DNO heat maps quarterly.

Best for: Projects that aren't time-sensitive and can wait 6–12 months for conditions to improve.

Ready to see what your land could earn?

Get an instant estimate of your potential solar farm income based on grid capacity in your area.

Calculate Now

How Do You Get a G99 Application Approved?

  1. Secure Land First: Never apply without a signed Letter of Authority from the landowner. DNOs now rigorously verify land rights.
  2. Check DNO Heat Maps: Most DNOs publish online capacity maps (e.g., UKPN Open Data Portal) showing red/green areas. Target areas with available capacity.
  3. Hire a Specialist: For anything over 50kW, the technical complexity typically requires a specialist electrical engineer.
  4. Consider Flexible Connections: You may get connected sooner by agreeing to "Active Network Management" (ANM), where the DNO can remotely curtail your output during rare peak congestion times.
  5. Progress Planning Early: With the new "First Ready, First Connected" rules, having planning permission significantly improves your queue position.
  6. Get a Budget Estimate First: Before investing in detailed designs, get a feasibility study to confirm grid availability.

Check Your Land's Solar Potential

Our free grid capacity checker analyzes your location and shows you exactly what your land could earn from solar development.

Calculate Now

Frequently Asked Questions

Frequently Asked Questions

G98 is for small systems under 3.68kW per phase (typically residential solar). G98 is 'install and notify' - you don't need approval before installation. G99 is for larger systems over 3.68kW per phase and requires formal DNO approval BEFORE you can install. Solar farms always require G99.
The DNO has 45-65 working days (approximately 3 months) to issue a Connection Offer after receiving your Standard Application Form. However, the actual grid connection date may be years away due to queue backlogs - some areas have connection dates of 2030-2036.
Assessment fees range from £500-£2,500 for HV connections, and £3,000-£8,000+ for EHV (33kV+). These are non-refundable. The actual connection cost ranges from £50,000 to over £2,000,000 depending on distance to substation and required reinforcement works.
Yes, you can submit a G99 application before planning, but the queue reforms mean projects with planning permission are prioritised. Having planning significantly improves your chances of securing a good connection date through the Gate 2 process.
A Letter of Authority (LoA) is a signed document from the landowner granting permission for the developer to apply for grid connection on their land. DNOs now rigorously check LoAs to prevent speculative applications that clog up the queue.
Common rejections are due to thermal constraints (local network is full), incomplete forms, or missing documentation. You can reapply after addressing the issues. If rejected due to capacity, consider a 'flexible connection' with Active Network Management (ANM).
The old 'first-come, first-served' queue has been replaced. Projects must now pass Gate 2 criteria (land rights + planning progress) to secure a connection date. Stalled 'zombie projects' are being terminated to free up grid capacity for viable projects.
For projects over 50kW, yes. The technical requirements (single line diagrams, fault level analysis, protection settings) typically require a specialist electrical engineer. Errors in the application cause delays and may result in rejection.
G100 allows you to install a larger system (e.g. 7.36kW) but caps grid export at a lower threshold (e.g. 3.68kW). It costs £300-£700 to apply and avoids costly grid reinforcement. Around 10% of G99 applications end up with export limitation. For commercial buildings with high self-consumption, G100 is increasingly a strategic choice — you use most power on-site anyway, so capping export loses very little revenue while dramatically simplifying the grid connection process.
The queue has been slashed from 722GW to 283GW — a 61% reduction. The old first-come-first-served system has been replaced with 'First Ready, First Connected'. Projects must pass Gate 2 criteria (land rights + planning permission) to secure a connection date. Gate 2 offers are being issued from May to November 2026. The reform is good news for viable projects — connection dates that were 2030-2036 are now being brought forward as 'zombie projects' are terminated.

Ready to Check Your Land's Solar Potential?

Our free grid capacity checker shows you exactly what your land could earn from solar.

Calculate Now